About the project
Leaves Builders were appointed to refurbish three classrooms used for animal care training and teaching. The project included installing new floor coverings, compact laminate units, new windows and blinds, new sinks, and water heaters. We also redecorated the walls and ceilings, relocated electrics (including sockets), and altered the heating system with a new electric heater to suit the new layout. With a tight 6-week schedule during the holidays, our team worked efficiently to strip out and fully refurbish the classrooms, ensuring minimal disruption.
CLIENT
Havant & South Downs College
CONTRACT TYPE
Direct
CONTRACT VALUE
£62,300
DURATION
5 weeks
SECTOR
Education

CASE STUDY
Southdowns College Animal Rooms